Mount Brydges sewage plant: costs, votes and lawsuit

Full title: Mount Brydges Sewage Treatment Plant · Written by John Farrugia

First publishedOctober 17, 2026
Last updatedOctober 27, 2026
Records checked up toOctober 17, 2026
Full report22 pages, with every source

This report explains why the Mount Brydges sewage plant has had trouble meeting its pollution rules, how the cost of fixing it grew, how Council voted, and why two neighbouring families are suing.

What happened

  • The Mount Brydges sewage plant was built in 2009-2012 on top of the old, closed township dump on Mill Road. Staff say it started having trouble removing ammonia, a pollutant in sewage, in 2018.
  • In June 2025 the Ministry of the Environment wrote that the plant was repeatedly releasing partly treated sewage, and asked the town for a short-term and a long-term plan.
  • The price of fixing it kept rising: about $8.5 million in December 2022, then about $13 million in a September 2025 staff estimate. In December 2025 Council hired a builder for $9.66 million, plus $966,000 for unexpected costs.
  • Neighbours and developer Sifton Properties asked Council to wait for a full environmental study first. In September 2025 two neighbouring families sued for $10 million. Their claims have not been proven in court.
  • On December 1, 2025 the families offered to put the lawsuit on hold if the rebuild waited for the study. Council approved the rebuild contracts that same night. The study is not expected to finish until fall 2027 - after the rebuild.

Why it matters to you

Millions of dollars are being spent to rebuild the plant on its current site before the study decides whether that site is right. Much of what residents would need to judge these decisions has not been made public.

Words with a dotted underline: tap them to see what they mean.

What the evidence shows

Shown in recordsTown documents, minutes or other official records show this.Reported, not provenSaid in the news, by a person, or claimed in court. Not proven by records.Still unansweredA question the records do not answer yet.

Key numbers

Engineers' estimate for the whole project, December 2022$8.5 million page 1
Staff estimate for the rebuild, September 2025about $13 million page 1
Construction contract, December 2025$9.66 million, plus $966,000 for unexpected costs page 1
Paid to R.V. Anderson for all its work, Jan 2024 - Sep 2026$1.42 million page 2
Amount the neighbouring families are suing for$10 million page 2
Green Municipal Fund low-interest loan for the construction$6.65 million page 5

Still unanswered

What's in the full report

Words used in this report

WWTF / WWTP
Short for wastewater treatment facility or plant - the sewage treatment plant.
Ammonia
A pollutant in sewage that harms fish; plants must remove most of it before releasing treated water.
RBC (rotating biological contactor)
The plant's original treatment units: large, slowly turning discs that grow the bacteria that clean sewage.
Extended aeration
A treatment method that pumps air into tanks so bacteria can break down sewage; the rebuild switches the plant to it.
Environmental assessment (EA), Schedule C
A formal provincial study of a project's effects and of other options, with public meetings; Schedule C is the most detailed kind.
Leachate
Polluted water that seeps out of a dump.
Sole source
Giving a contract to one firm without inviting competing bids.
Retainer
A standing arrangement that lets staff hand a firm work without a separate Council vote each time.
Recorded vote
A vote where each member's yes or no is written in the minutes.
Contingency
Extra money set aside in a contract for unexpected costs; it is only spent if needed.

Updates and corrections

Every change to this report is listed here. An Update adds new information. A Correction fixes a mistake. A Minor change is wording, layout or branding only.

This page is a short guide to the full report. If they ever seem to differ, the full report is the record. Questions or corrections: [email protected].